The bathroom are now fully functional and I can take a shower in it, but only in cold water. It will only be a few days before the hot water is connected as the installation of the heater started Friday, in the courtyard. Only thing missing is the mirror, the light above it and the door.
Thursday the first batch of exterior doors and windows arrived.
The first windows was installed in the living room, but the second came with the wrong measure and has to be refactored (still don't know how long that will set us back on delivery).
The first door was installed in the common hallway towards the courtyard.
The door is half glass, half vented blinds and will be used to close off the hallway from the courtyard.
I expect the door to be open most of summer 24/7 and closed most of winter 24/7.