Groundfloor apartment electrics complete
Sun, 27 Sep 2026 10:20:00 UTC


Thursday 24th September 2026, the electricians finished the ground floor apartment electrics. The apartment is now ready for the wall tiles to go up once the kitchen is install.

There are two remaining jobs to be completed by the electricians; The intercom system and the segregation of the electric circuits for the common space, the ground floor apartment and the first floor apartment.
The intercom system broke wall to create a buzzer, we had forgotten about, on the inside to open the front door, when leaving the buiding.

Speaking of kitchen and other deliveries, we are still waiting for the kitchen to be delivered. The ETA is still the upcomming week - fingers crossed.
Other deliveries expected in the upcoming week includes the RO drinking water system, including the filtersystem, tubes and countertop tap.


Wednesday had the new vanity lights come up. Other than that check-out more pics in the gallery and before/after section.